Deliverables

Year 1 | Year 2 | Year 3 | Year 4

Year 1

Del. no. Deliverable name WP no. Planned delivery date Actual delivery date Status Comments
2.1

Design report of quadrupole magnets

2 M3 25/05/2013 Submitted Report
2.2

Design report of sextupole magnets

2 M3 05/07/2013 Submitted Report
1.1

Relevant Protocol addenda agreed between CERN and SESAME

1 M4 12/12/2013 Submitted Report is restricted
2.3

Design report of bending magnets

2 M5 09/02/2014 Submitted Report
1.2

Formal agreement signed between CERN and ALBA-CELLS

1 M7  22/10/2014 Submitted Report is restricted

Year 2

Del. no. Deliverable name WP no. Planned delivery date Actual delivery date Status Comments
5.1

Technical specifications for the power supplies

5 M14 19/06/2014 Submitted Report
3.1

Prototype quadrupoles delivered

3 M15 14/10/2014 Submitted Report
3.2

Prototype sextupole delivered

3 M15 14/10/2014 Submitted Report
3.3

Prototype dipole delivered

3 M18 10/04/2015 Submitted Delivered late due to the delay of the supplier. Report
4.1

Report of the measurement of the prototype combined function dipole

4 M21 24/11/2015 Submitted Delivered late due to the late delivery of the dipole. Report
4.2

Measuring bench for the quadrupoles and sextupoles commissioned at SESAME

4 M22 17/06/2015 Submitted Report
1.3

Periodic report years 1&2

1

M24 17/12/2014 Submitted Report

Year 3

Del. no. Deliverable name WP no. Planned delivery date Actual delivery date Status Comments
3.4

32 focusing and defocusing quadrupoles, long, plus 1 spare magnet and 1 set of coils

3 M32 08/03/2016 Submitted Delayed to M38 due to fabrication. Work performed. Report
3.5

64 focusing and defocusing sextupoles, plus 1 spare sextupole and 2 sets of coils

3 M32 21/03/2016 Submitted Delayed to M38 due to fabrication. Work performed. Report
5.2

Power supplies with acceptance documents

5 M34 04/04/2016 Submitted Delayed to M42 due to change of strategy. Work performed. Report
3.6

16 dipoles magnets, plus 1 spare dipole and 1 set of coils

3 M36 07/04/2016 Submitted Delayed to M38 due to fabrication. Work performed. Report

Year 4

Del. no. Deliverable name WP no. Planned delivery date Actual delivery date Status Comments
4.4

Results of all quadrupole and sextupole measurements in relevant database

4 M37 29/04/2016 Submitted

Delay linked to 3.4 and 3.5. Work performed. Report

4.3

Results of all dipole measurements in relevant database

4 M38 29/04/2016 Submitted

Delay linked to 3.6. Work performed. Report

1.4

CERN-EC-SESAME Communication on Science for Peace in the Middle-East

1 M48 14/12/2016 Submitted

Report

1.5

Summary on training and knowledge transfer

1 M48 21/10/2016 Submitted

Report

1.6

Periodic report years 3&4 and final report

1 M48

09/01/2017

30/01/2017

Submitted

P2 report

Final report

6.1

Report on CERN power supply integration, hardware and beam support for magnet and commissioning

6 M48 14/12/2016 Submitted Report