Year 1 | Year 2 | Year 3 | Year 4
Year 1
Del. no. | Deliverable name | WP no. | Planned delivery date | Actual delivery date | Status | Comments |
---|---|---|---|---|---|---|
2.1 |
Design report of quadrupole magnets |
2 | M3 | 25/05/2013 | Submitted | Report |
2.2 |
Design report of sextupole magnets |
2 | M3 | 05/07/2013 | Submitted | Report |
1.1 |
Relevant Protocol addenda agreed between CERN and SESAME |
1 | M4 | 12/12/2013 | Submitted | Report is restricted |
2.3 |
Design report of bending magnets |
2 | M5 | 09/02/2014 | Submitted | Report |
1.2 |
Formal agreement signed between CERN and ALBA-CELLS |
1 | M7 | 22/10/2014 | Submitted | Report is restricted |
Year 2
Del. no. | Deliverable name | WP no. | Planned delivery date | Actual delivery date | Status | Comments |
---|---|---|---|---|---|---|
5.1 |
Technical specifications for the power supplies |
5 | M14 | 19/06/2014 | Submitted | Report |
3.1 |
Prototype quadrupoles delivered |
3 | M15 | 14/10/2014 | Submitted | Report |
3.2 |
Prototype sextupole delivered |
3 | M15 | 14/10/2014 | Submitted | Report |
3.3 |
Prototype dipole delivered |
3 | M18 | 10/04/2015 | Submitted | Delivered late due to the delay of the supplier. Report |
4.1 |
Report of the measurement of the prototype combined function dipole |
4 | M21 | 24/11/2015 | Submitted | Delivered late due to the late delivery of the dipole. Report |
4.2 |
Measuring bench for the quadrupoles and sextupoles commissioned at SESAME |
4 | M22 | 17/06/2015 | Submitted | Report |
1.3 |
Periodic report years 1&2 |
1 |
M24 | 17/12/2014 | Submitted | Report |
Year 3
Del. no. | Deliverable name | WP no. | Planned delivery date | Actual delivery date | Status | Comments |
---|---|---|---|---|---|---|
3.4 |
32 focusing and defocusing quadrupoles, long, plus 1 spare magnet and 1 set of coils |
3 | M32 | 08/03/2016 | Submitted | Delayed to M38 due to fabrication. Work performed. Report |
3.5 |
64 focusing and defocusing sextupoles, plus 1 spare sextupole and 2 sets of coils |
3 | M32 | 21/03/2016 | Submitted | Delayed to M38 due to fabrication. Work performed. Report |
5.2 |
Power supplies with acceptance documents |
5 | M34 | 04/04/2016 | Submitted | Delayed to M42 due to change of strategy. Work performed. Report |
3.6 |
16 dipoles magnets, plus 1 spare dipole and 1 set of coils |
3 | M36 | 07/04/2016 | Submitted | Delayed to M38 due to fabrication. Work performed. Report |
Year 4
Del. no. | Deliverable name | WP no. | Planned delivery date | Actual delivery date | Status | Comments |
---|---|---|---|---|---|---|
4.4 |
Results of all quadrupole and sextupole measurements in relevant database |
4 | M37 | 29/04/2016 | Submitted |
Delay linked to 3.4 and 3.5. Work performed. Report |
4.3 |
Results of all dipole measurements in relevant database |
4 | M38 | 29/04/2016 | Submitted |
Delay linked to 3.6. Work performed. Report |
1.4 |
CERN-EC-SESAME Communication on Science for Peace in the Middle-East |
1 | M48 | 14/12/2016 | Submitted | |
1.5 |
Summary on training and knowledge transfer |
1 | M48 | 21/10/2016 | Submitted | |
1.6 |
Periodic report years 3&4 and final report |
1 | M48 |
09/01/2017 30/01/2017 |
Submitted | |
6.1 |
Report on CERN power supply integration, hardware and beam support for magnet and commissioning |
6 | M48 | 14/12/2016 | Submitted | Report |